Leaseholders living in high rise flats which still need essential fire safety work are worried how long it's taking to get it started.
The Local Democracy Reporting Service understands that a works contract to rectify a number of fire safety and non-fire safety defects at the Celestia apartments complex in Cardiff Bay was supposed to be signed earlier this month.
But leaseholders have accused the developer behind the apartments, Barratt Redrow, of continuing to add clauses to the contract which is preventing it from being signed.
The company is one of the major developers in Wales that has signed the Welsh Government’s building safety pact and has said it is prepared to carry out and pay for works to address fire safety and non-fire safety external façade defects.
Information shared with leaseholders by Celestia Management Company Limited (CMCL) updating them on progress to put their homes right shows that a works contract was expected to be signed last month.
A timeline claims that Barratt Redrow continued to add clauses to the work contract “in their favour” in April.
Getting the works contract over the line would begin the process of fixing two major issues leaseholders have been fighting to get sorted for years.
These include the addressing of external wall fire defects and wooden cladding and the replacement of render on the sides of buildings which has come loose at certain sections in the past.

Barratt Redrow said it remained “poised” to start remediation work at Celestia and that it had a positive meeting with the building’s management company recently.
The impact of issues affecting Celestia go beyond safety concerns, according to people living there.
Leaseholders are having to pay ever increasing service charges and some have expressed doubt over whether or not they will be able to sell their homes in the future.
A spokesperson for Barratt Redrow said: “At Celestia, we remain poised to start remediation works in line with our commitments under the Welsh Government’s pledge deed of bilateral contract."
“Following a positive meeting with the Celestia management company last week, we are hopeful that the works contract will be agreed imminently.”
Following a lengthy legal process, leaseholders at Celestia welcomed Redrow’s offer in April 2024 to fund and undertake remediation work.
Leaseholders are also trying to get Barratt Redrow to accept responsibility for a number of other non-fire related defects.
These include issues with soil stacks, water ingress on windows and the flooding of a nearby path that goes along the dockside.

All large developers in Wales have signed a Welsh Government building safety pact which requires them to make all buildings of 11m or more in height fire-safe.
However, many leaseholders and residents in high-rise buildings are still waiting for work to be completed and continue to call for developers to be made responsible for fixing other faults not related to fire safety.
Last December, a Welsh Government update on building remediation across the country showed work had been completed on 83 out of 433 buildings in the Welsh Building Safety Programme.
Of those buildings, 252 are private tenure buildings and 181 are social housing buildings.
The Welsh Government’s update at the time also showed that work had started on 102 buildings and that plans were in development for work on a further 206 buildings. Seven buildings do not require any fire safety works.
They are also working with the developers behind the remaining 35 buildings to identify any remediation needs.

Penarth school project sparks Welsh language transformation
South Wales and Gwent Police introduce new online portal for crime victims
Penarth Pier Pavilion Cinema awarded £65,000 for major equipment upgrade
New Cafe could be coming to High Street, should plans be approved
Reform MS Sarah Cooper-Lesadd has defected to Plaid Cymru
Public sector broadcasters facing “huge challenges”, according to Wales’ culture minister
Welsh Government Plans 30% Rates Cut for Hospitality and Leisure Businesses
Loan scheme to help bring landmark Cowbridge building back into use
Women less likely to receive lifesaving CPR as Calon Hearts calls for more realistic training
Shortlist announced for 2026 Vale and Bridgend Business Awards
Vale Council to Consider Changes to Recycling and Waste Services
Plan to change the face of a Welsh village
1,000 children vaccinated against Hepatitis A in Barry but there’s still time to protect your child
Plans have been approved to convert offices into a bedsit in Barry, despite police concerns
Police Appeal for Witnesses after Penarth Road collision
Penarth teacher to appear in new fly-on-the-wall S4C series
Barry Athletic bowler is county champion
Penarth Athletic launches public consultation on major rebuild nine months after devastating clubhouse fire
Barry Learner Secures Place to Study Medicine After Transformative Return to Education
Detectives release e-fit in Barry sexual assault investigation